Pavement reconstruction phase complete, however, due to rain, traffic delineation was not placed. With the
forecasted unsettled weather, road will remain closed to December 11, 2026 or until the road can safely be
reopened.
Road base reconstruction and asphalt paving complete. Other remaining items of work include roadside
shoulder work, driveway conforms, and drainage ditch work.
Work Schedule
➢ October 26, 2026 – December 11, 2026
• The road will be closed to through traffic.
• Pavement Traffic Delineation, pending weather.
• Roadway shoulder work.
• Remaining drainage ditch work.
• Most construction activities will take place from 7:00 a.m. to 4:30 p.m. for day work and from 7:00
p.m. to 5:00 a.m. for night work.
Access will be provided to residents living within the work zone to get to their homes. No weekend work is
anticipated. Motorists can bypass the closure via US Highway 101.
In the event of an emergency, emergency responders will be afforded priority through the work zone, regardless
of whether construction occurs during daytime or nighttime hours. PWFP will make every effort to minimize
traffic disturbances, maintain access through the work zone, and efficiently move from one phase of
construction to the next.
The County of Monterey encourages motorists to use caution when traveling through the construction area and
to follow all posted signs, traffic control devices, and flagger instructions.
Granite Rock is the prime contractor for this project.