Pavement reconstruction phase complete, however, due to rain, traffic delineation was not placed. With the forecasted unsettled weather, road will remain closed to December 11, 2026 or until the road can safely be reopened. Road base reconstruction and asphalt paving complete. Other remaining items of work include roadside shoulder work, driveway conforms, and drainage ditch work. Work Schedule ➢ October 26, 2026 – December 11, 2026 • The road will be closed to through traffic. • Pavement Traffic Delineation, pending weather. • Roadway shoulder work. • Remaining drainage ditch work. • Most construction activities will take place from 7:00 a.m. to 4:30 p.m. for day work and from 7:00 p.m. to 5:00 a.m. for night work. Access will be provided to residents living within the work zone to get to their homes. No weekend work is anticipated. Motorists can bypass the closure via US Highway 101. In the event of an emergency, emergency responders will be afforded priority through the work z...